Warringal Redevelopment Revised Timeline

Below is a timeline detailing the Warringal Private Hospital redevelopment project, highlighting the project's future and completed key events and milestones.

Mid 2022

  • Funding Approved/Planning Permit received and project announced
  • Builder appointed (Kane Constructions)
  • Construction Commences: Tower 1 extended to provide three additional in-patient units

Late 2023

  • Completion of Tower 1 extension - commissioning of new in-patient units
  • Decanting and demolition of Conder and Streeton building
  • Construction Commences: Tower 2 Clinical Services Building

Early 2024

  • Completion of 2 operating theatres & new centralised recovery unit

Mid 2024

  • Completion of an additional operating theatre
  • Tower 1 re-cladding works

2024 - 2025

  • Major construction continues of Tower 2, New Emergency Department and back of house stores

Late 2025

  • Opening of New Emergency Department and Tower 2 (ICU, DOSA, In-Patient Units, Med Imaging, Consulting, Car parking)

Early 2026

  • New Main Entry and Pharmacy

More Updates Coming Soon